2023: eco-renovation of the former Constant bank office

6 days ago
2 min read

Why the building work?

Major work is planned to restore the estate to its former glory: besides the house, which needs freshening up, the entrance pavilions had not been lived in since the 1970s for the left-hand pavilion, and for much longer for the right-hand one. Our efforts have so far focused on the left-hand entrance pavilion, and will continue with some refurbishment of the house and upkeep of the park, followed by the right-hand pavilion, the entrance gate and finally the outbuildings.


Renovating, yes, but with respect: our eco-renovation ambition

For the renovation, we wanted to combine our ecological convictions with our desire for things done beautifully and well. To do so, we spent a considerable amount of time looking for the right craftspeople, the right products and the right materials. As far as possible, we chose products of French origin. The insulation was done with ecological materials (flax, wool and hemp), more expensive certainly, but also healthier than mineral wools. The paint was chosen for its very low emission of volatile pollutants, so as to live in a healthy environment. Finally, anxious not to spoil the character of the pavilion's interior, we chose to reuse the doors and skirting boards and to respect the volume of the existing rooms.


Timeline of the eco-renovation work carried out in 2023:


February 2023

  • Purchase of Maison Constant and clearing of the left-hand pavilion.

  • Clearing of furniture from different periods (Louis XVI, Louis Philippe, Empire, etc.) left by successive former owners.

  • Removal and storage of the skirting boards, doors and hexagonal terracotta tiles for reuse.


  • Dépose à la main des tomettes
  • Décaissement des tomettes posées sur du sable
  • Tas de tomettes hexagonales


March - May 2023

Complete renovation of the pavilion's interior: an insulating slab on the ground floor, insulation of the walls and ceiling, installation of mechanical ventilation, complete electrics and plumbing.

 

June 2023

Application of the floor plaster made by Plâtres Vieujot on the ground floor by the artist Carine Delalande, and fitting of traditional "mouton et gueule de loup" casement windows. Paint tests and painting of the shutters.

 


  • Essai de peinture sur les volets
  • Mise en peinture des volets


June to November 2023

The finishing touches. The devil is in the detail and we are fairly demanding, so the finishing took us a long time. The plasterwork, painting and decoration were done during this period, together with furnishing the interiors using furniture already on the estate.

 

December 2023

First rental

 

April 2024

Masonry work, with the corner stones and façade mouldings restored, the window sills renovated and damaged stones replaced by a mason specialising in old buildings and committed to eco-renovation.


For more information or to make a booking, click here.


 
 